Saturday, 31 October 2015
Carpet install
Deck staining
Using the last of the mild weather we were able to stain out exterior cedar decks and stair landings. The building is now nearly ready for the condo registry process.
Tuesday, 20 October 2015
Hardwood tile transitions
Having a seamless transition between flooring surfaces is generally the preferred approach. The skilled tradespeople we hire know exactly how to do this, and the tiled foyer to living room hardwood transition is a classic example.
Hardwood is now complete in the first unit. Next up is finalizing the tile and the plumbing.
Permeable paver install for visitor parking stall
The city issued a requirement that the project feature a permeable geotextile material be installed as the driving surface of the visitor parking stall.
To deal with this requirement we located a new supplier that stocks the material and began the install today. First the parking stall was levelled and bladed with the skid steer. Crushed material was added and compacted and raked. Finally the ecogrid blocks were put down. Later we will purchase some pea gravel and fill in the ecogrid material.
Monday, 19 October 2015
Hardwood install begins
The installer has started laying the hardwood. Because it is wide plank engineered oak, it must be glued and nailed. The large pieces means that the install goes quite quickly.
Sunday, 18 October 2015
Grouting tile
Our Tilesetter crew is now completing a few rooms and applying the grout. Hardwood flooring is booked to begin tomorrow.
Saturday, 17 October 2015
Landscaping begins at the threeplex
Taking full advantage of the warm autumn weather we were able to start the landscaping process at the threeplex. In the rear area two deciduous trees and a variety of shrubs were dug in and generously surrounded with a compost loam mixture. Cover will be added in the form of a mulch later.
Friday, 16 October 2015
Natural stone shower base
Quartz countertop
Our first house had the countertop surfaces templated last week. The material was delivered today and installed along with the three bathroom sinks and the kitchen sink. All sinks we are using are undermount style which makes for a much nicer finish.
Wednesday, 14 October 2015
Stucco completion
Under ideal weather conditions our acrylic stucco was completed today. The smooth finish complements the quality work done by the prep crew to endure such a nice outcome.
Tuesday, 13 October 2015
Stucco acrylic application
Tuesday, 6 October 2015
Tile prep
With the kitchen complete in the first unit we can now begin the tile. Our crew is prepping the water proof walls in the shower in the basement and will soon be installing the custom tile we selected. Ditra underlayment material is also installed on the basement floor.