Monday, 19 October 2015

Kitchen backsplash tile

Our kitchen backsplash is tiled and ready to grout 


Sunday, 18 October 2015

Grouting tile

Our Tilesetter crew is now completing a few rooms and applying the grout. Hardwood flooring is booked to begin tomorrow. 




Saturday, 17 October 2015

Landscaping begins at the threeplex

Taking full advantage of the warm autumn weather we were able to start the landscaping process at the threeplex.  In the rear area two deciduous trees and a variety of shrubs were dug in and generously surrounded with a compost loam mixture.  Cover will be added in the form of a mulch later.  


Friday, 16 October 2015

Natural stone shower base


Our master bathroom shower will feature a natural stone base. The variety we often use is a flat cut pebble.  It features a very natural stone appearance with a surface that is comfortable on the feet.  





Quartz countertop

Our first house had the countertop surfaces templated last week. The material was delivered today and installed along with the three bathroom sinks and the kitchen sink. All sinks we are using are undermount style which makes for a much nicer finish. 




Wednesday, 14 October 2015

Stucco completion

Under ideal weather conditions our acrylic stucco was completed today. The smooth finish complements the quality work done by the prep crew to endure such a nice outcome. 


Tuesday, 13 October 2015

Stucco acrylic application


Our crew has returned to apply the acrylic stucco to the cured sand and cement scratch coat.  Significant progress was made on day one and more than likely the job will be complete tomorrow. This final exterior stage allows a total site cleanup to take place and for landscaping to begin. 



Tuesday, 6 October 2015

Tile prep

With the kitchen complete in the first unit we can now begin the tile. Our crew is prepping the water proof walls in the shower in the basement and will soon be installing the custom tile we selected. Ditra underlayment material is also installed on the basement floor.