Thursday, 25 February 2016
Landscaping in February
With possession of our first two homes complete we can turn out attention to landscaping. Odd as it sounds we are able to finish some landscaping in February due to the warm temperatures and lack of snow.
Tuesday, 16 February 2016
Trade turnover
With every project we take the time to reflect on what crews we liked best and what contractor gave us the most trouble.
Needless to say that leads to someone being cut from our A team each project. It also gives us a chance to constantly locate newer and possibly superior trades.
We brought on new painters and electricians this project. They both did well and have been approved for future use. We had some trouble with a few other individuals and they won't be back. Let's hope our next job is crafted even better!
Second sale complete - what comes next?
Our second new owner has not taken the keys to his new house. Last weekend we had an open house in our last and final unit at the threeplex to be completed.
This means we are hearing the same question from a lot of our trades and clients - what's next ?
Right now we don't have a project in the ground because the frenzied marked of the last few years raised land prices beyond a sensible level. We didn't buy another townhouse site (luckily) in part because supply was so limited.
Now that the market has cooled significantly we haven't seen many properties priced to reflect our reality of what it costs to build a project. Until we do we cant acquire more land. Sellers have proven highly resistant to dropping their land prices. In fact most land appears to be in builder inventories and the are perhaps the most stubborn bunch when it comes to taking a loss on raw land...
Friday, 15 January 2016
LED pot lights
Recently the entire industry has started shifting to led lighting. Most lights we are using now are led and in particular we are including all led pot lights on dimmers as a no cost upgrade to our buyers.
First sale confirmed
Our show home has sold at the threeplex project. With the close of the sale we will set up the second unit as the show suite. Please visit us there soon!
Friday, 4 December 2015
Trade craftsmanship and construction material in Calgary - a complex topic
Often the 'old times' are referenced when it comes to construction and how good it 'used to be'. I don't actually know much about building before the late 90's, however I have torn down a bunch of houses and they were, without exception, awful. True, they had better lumber back then, but mostly the homes I have destroyed were about 60 years old and just nasty, defective, smelly relics.
The building code is far more stringent and the materials vastly superior today. For example, wiring, furnaces, appliances, cabinetry and countless other products are designed with technology and materials unheard of in the post war period. We now feature LED lighting as a standard in our pot lights, this was cost prohibitive just a few years ago.
While materials are far better, what about craftsmanship? Today's fast pace and the pressure to get stuff done can frequently interfere with getting the material installed with the care and attention the client deserves. For the most part we have been able to hire good crews and we are impressed with the technical work that is done. Here is a good example of the electrical panel we had recently completed. Not likely possible 50 years ago!
Master bathroom update - house 2
Lots of progress to report at house two. With tile grouted, shower glass installed, and freestanding tub in place with tub filled, we are nearing completion. Here are some photo updates from today
Sunday, 22 November 2015
Project Retrospective - threeplex
With our first unit of the threeplex project complete, many inspections passed and our first very successful open house hosted, now is as good a time as can be to do a little project overview.
This post is sort of a follow up to our most highly read post to date, http://rebuildcalgary.blogspot.ca/2015/03/why-does-it-cost-so-much.html where we describe in some detail why it is so costly to build inner city homes in Calgary. In summary, we put forth an argument that house building costs so much because the authority in our society wants it to be so, due to its self interest. In addition, the non construction related costs of the project are high, and increasing, and add little value to the end user that inevitably has to pay the higher cost of the project.
Below we will lay our a few categories of the project, and self evaluate ourselves in terms of how we managed the project.
This post is sort of a follow up to our most highly read post to date, http://rebuildcalgary.blogspot.ca/2015/03/why-does-it-cost-so-much.html where we describe in some detail why it is so costly to build inner city homes in Calgary. In summary, we put forth an argument that house building costs so much because the authority in our society wants it to be so, due to its self interest. In addition, the non construction related costs of the project are high, and increasing, and add little value to the end user that inevitably has to pay the higher cost of the project.
Below we will lay our a few categories of the project, and self evaluate ourselves in terms of how we managed the project.
- Design and layout - Grade B+. Much of the credit here has to be attributed to our design team which consists of Inertia (Trent) - drafting and permitting, and Denca (Mikaela) - cabinetry design and creative assistance. Without these two our product would be far inferior. We can give ourselves a little credit here for issuing the design brief upon which the team was able to generate the plans, and for our careful execution of the construction. Even getting this project approved by the city was a major blessing, without the design experience and negotiation skills of our team the project could have stalled or been rejected.
- Budgeting - Grade B. Remarkably we have stayed on budget, and we have invested regularly in budget update and forecast sessions with our accountant to stay on top of changes. Our vigilance here has paid off and we put more effort into budgeting and forecasting than we did previously. We have worked tirelessly to remain on budget and this led to some very tough decisions and broken relations when we said goodbye to a bunch of trades we had come to rely on. Essentially we woke up to the reality of a recession faster than many of our trades did, and some had to be let go. Our early budget proved to be weak and we got off to a poor start. We encountered a city requirement that couldn't be overcome without some geotechnical engineering and foundation shoring. This costly exercise eventually proved futile, but by then we had spent $15k, which represented half of our project contingency fund. We stared down an ugly reality that we had hardly started the project and had burnt half the budget safety net. To combat this we tirelessly attacked other project elements to seek out savings and economies. To our credit we restored our contingency budget by about the halfway point of the project.
- Supervision - Grade B -. Unfortunately here we fell into a trap again, where slow framing had a major cascading impact on our schedule. Losing a month here very nearly cost us the ability to finish the exterior of the building on time and to get the landscaping inspected and approved before winter set in. Another problem became slow house wrapping and stucco prep that delayed the stucco, caused all kinds of landscaping delays and added a lot of mess and cleanup problems that could have been avoided. We have suffered from slow framing on multiple occasions now, and it appears we just are not learning our lesson. Expect major changes here in our approach next time. On the other hand, the bulk of the schedule has run smoothly. Many of our trades have pleased us with their performance, including some of the new crews we have brought on. Our supervisory execution has been harmed in part by circumstance beyond our control. Due to the change in the economy we have taken on more hands on construction work than we had planned. In fact we took on too much, and this led to some difficulty in performing the supervisory duties such as advance ordering of material and timely material delivery.
- Interior decoration - Grade B+. Based on early reaction to our design and material selection, it appears our design scheme has been very well appreciated by visitors to the site. Many favourable comments have been received about the quality and appearance of the flooring, cabinetry, and tile. We really worked hard here to come up with our own signature style. Full pictures are available here. https://drive.google.com/folderview?id=0B4SACAcBIaNIWmxYYWctZV9fTmc&usp=sharing
- Time of build - Grade B. This is similar to the supervision category. We could have removed a month of construction time from the project had we been able to finish the framing and exterior sooner. Otherwise the schedule has been followed closely.
- Marketing - Grade B. We switched to marketing through www.newinfills.ca. It has proved to be a good choice and they have provided better marketing tactics than we have had in the past. Unfortunately the market is weaker so no presales were possible. In a stronger market two of the units likely would have sold long ago.
- City inspections - Grade B+. We had some very challenging details to execute and thus far the inspections have passed without major difficulty. We hope this continues into the final occupancy inspection.