Our threeplex foundation project is progressing at a remarkable rate given the amount of work involved. Cribbing took the crew about one and half days (six man crew) and the pour is booked for this afternoon.
The engineer visited the site to inspect the rebar grid in the walls before they were covered up this morning. A 12 inch grid of rebar was placed in the perimeter walls to support the wall against the weight of the high backfill.
And finally the concrete arrived in the late afternoon
As per usual practice the pump truck allows quick filling of the nine foot forms