Thursday 18 September 2014

Stair railing and cladding complete


With the stair railing and cladding finished, we can prep the house for painting of the doors and trim, and the staining of all the stair material.  The railing job required about two weeks of patient labour, and the end product is very nicely done.  We may adjust our stair supplier next time we do such a complex stair in order to make the site work a little easier, as we have found that our railing carpenter likes to build the stairs himself in his shop.

the stairs viewed from the dining room after the dust is swept out and the many tools packed away



looking down from the second floor

looking up toward the skylight from the basement
nice hardware was located for the hand rail bracket

The final piece of maple that completes the job

No comments: