Monday 31 August 2015

Underground utilities complete/furnace startup

The city electrical inspector arrived to inspect the three new meter bases.  His approval along with new account creation for each of the new services allows for use of electricity within each of the houses (no more stringing extension cord through doors and windows). 

With gas available we were also able to start the furnace in the house with the most advanced taping. With quicker compound drying the tapers will be able to work more efficiently. 

Green sticker means new meters can be installed. 


First ignition of furnace and after some air pockets are released 

Furnace is running smoothly and temporary thermostat can regulate the heat. Drywall compound can now dry properly overnight. 

No comments:

Post a Comment