Thursday 28 May 2015

End of May progress

Recently we had a few major milestones overcome at the site.  The city water connection was made in the front yard and gas was connected at the rear.  Plumbing was roughed in and inspected along with electrical conduits so we can prep the basement slabs and hopefully pour them soon.  We want to have the basements framed before the framers finish upstairs, that way the furnace and electrical installations and plumbing can proceed all in one step. Framers are moving into second floor framing and trusses and windows are paid for and delivery arranged. 

At this time we are scheduling the post framing trades and will be planning the garage and exterior finishing. We are also now ready to finish the kitchen and fireplace designs and have shop drawings prepared for those key components. 

Sump pump, electrical conduit and water main are prepped for the basement slab pours. 


Upper stairs arrive the easy way on the zoom boom 