Saturday 12 July 2014

Garage framing

With lumber and trusses on site, our framers have returned following the completion of another house   framing job elsewhere.  Framing of the garage is about a three day project.  With electrical already booked, and man-doors and car-doors in the process of being ordered, we will attempt to get the garage stucco done at the same time as the house.  The garages here will get insulated and drywalled as well.  We are also planning to do a side mount garage opener on one of the garages.  This should free up some much needed space on the ceiling to store off season gear and other bulky but not temperature sensitive items.